Introduction

This chapter describes the recommended improvements to the transportation system in Marion County that make up this Plan. Recommendations regarding each mode of transportation are dealt with individually.

It should be emphasized that the recommendations made here are designed to work together as a system. Piecemeal implementation will mean that problem areas will remain unresolved, or that new problems will be created. For example, construction of a new connection from I-79 to downtown Fairmont without improvement of access to the Locust Avenue area would almost certainly result in a deterioration of conditions in downtown and would fail to resolve pressing traffic congestion problems elsewhere.

The basic tool used to evaluate the effectiveness of the various proposals for transportation improvements in Marion County was the QRS-II computerized travel demand model. The QRS-II model, which has been used by WVDOT on transportation planning projects throughout the State of West Virginia, allows transportation planners to test the consequences of adding new components to the transportation system or making improvements to existing components.

The model development and testing process for Marion County has been summarized in a separate Technical Report provided to the WVDOT. It should be emphasized that the use of a travel demand model does not always provide clear-cut answers to thorny transportation planning issues. Rather, the results of the modeling process must be interpreted and tempered with knowledge of on-site conditions and the context within which the transportation planning process occurs. The model is primarily useful in understanding how new or improved facilities will interact with the already complex transportation system now in place.

Issues related to the phasing and funding of these recommended projects are discussed in the following section of this report. However, it is worth stating that there are recommendations included in this Plan that are relatively inexpensive and easily implemented. There are also very costly recommendations. As a general rule, it is advisable to begin by implementing the less challenging improvements while also commencing work on the larger projects.

A large roadway construction project is a time-consuming and complex undertaking. The time span required to move from initial planning through preliminary engineering, environmental studies, preparation of final construction plans, right-of-way acquisition, and actual construction is measured in years. To complete such a project can easily take five to ten years.

Roadway Element

Prior to discussing the recommendations growing from this study, it is important to first state the assumptions that have been made regarding projects to which commitments have already been made and which have been programmed for completion in the near future. The projects in Marion County that fit within this description are:

  1. Reconstruction of the Jefferson Street Bridge in Fairmont (now underway);
  2. Replacement of the Blackshere Bridge on US 250 near Mannington (now underway);
  3. Replacement of the US 19 Bridge at the Harrison County Line (now underway);
  4. Widening of CR 73/73 from US 250 to the I-79 overpass in White Hall (now underway);
  5. Replacement of the Bellview Bridge on US 19 crossing Buffalo Creek in Fairmont;
  6. Replacement of the Benton’s Ferry Bridge in Pleasant Valley;
  7. A new interchange on I-79 at Eldora; and
  8. Replacement of the Hough Street Bridge in Mannington.

Recommended Roadway Improvements

Figure 7 illustrates the roadway improvements called for in this Plan. The supporting logic behind the improvements is explained and illustrated in more detail in the section that follows. Figure 8 illustrates the projected traffic volumes expected to use the various components of the recommended system in the year 2020. The volumes were established using QRS-II travel demand model developed as part of this study. Table 4 lists the measures of performance for the recommended plan network. Performance is measured in comparison to the Base + Committed network, which includes the existing roadway network and the added components listed above.

The measures of performance, which are calculated for a typical 24-hour period, include:

  • Vehicle miles traveled (VMT) is the total number of miles traveled by all vehicles on the roadway network over a 24-hour period;
  • Percent of congested travel is the percentage of all vehicle miles traveled which occur on roads which are congested as calculated based on V/C ratios, and
  • Percent of congested route miles is the percentage of route miles on which congested conditions at some time during the typical day.

Table 5 indicates the existing traffic volumes and the projected future traffic volumes at various key points on the recommended plan network for the year 2020. The volumes shown in Table 5 are basically derived from the QRS-II modeling process. The WVDOT also makes traffic projections based on formulas developed at West Virginia University Engineering Department. While these formulas are useful in developing traffic projections in

Table 4 - Fairmont/Marion County Multi-Modal Transportation Plan
Measures of Network Performance
Based on Forecast 2020 Traffic Volumes

 

Base Plus Committed

Recommended
Plan

Percent
Change

VMT

5,544,038

5,674,920

2.4%

% Congested Travel Miles

31.7%

27.1%

-14.6%

% Congested Route Miles

18.7%

17.4%

-6.8%

the absence of more detailed travel demand modeling, they do not incorporate a recognition of the complex interaction of changes in the overall transportation system made possible by travel demand modeling. On the other hand, a weakness of the travel demand modeling process is that it does not incorporate outside influences very well. For example, travel demand modeling may not be the best approach to projecting through traffic on I-79. Thus, the WVDOT projection formula was utilized to forecast future volumes on I-79 passing through Marion County.

Figure 7 - County Improvements

Figure 8 – Future Traffic

Table 5 - Fairmont/Marion County Multi-Modal Transportation Plan

Projected Future Traffic Volumes (2020)

Base + Committed Network vs. Recommended Plan Network

Facility

Approximate Location

1997 Volume

Base +
Committed

Rec.
Plan

I-79

Marion County/Monongalia County line

28,000

61,900

61,900

Between CR 33 and WV 310

31,000

60,900

60,900

Between WV 310 and I-79/Downtown Con.

31,000

NA

68,600

Between I-79/Downtown Con. and CR 64

31,000

NA

72,100

Between WV 310 and CR 64

31,000

60,800

NA

Between CR 64 and CR 64/1

33,000

65,700

66,700

Between CR 64/1and US 250

33,000

66,800

68,600

Marion County/Harrison County line

31,000

59,600

59,600

 

US 250

Between CR 250/4 and CR 2

1,500

1,800

1,800

Between CR 6/1and CR 250/5

1,900

2,000

2,000

Between CR 250/6 and CR 1

3,100

3,100

3,100

Between CR 1 and CR 11

9,000

9,200

9,300

Between CR 11 and CR 91

9,400

9,500

9,600

Between CR 50 and WV 218

8,900

9,000

9,000

Between CR 23 and CR 250/32

5,200

5,600

6,800

Between CR 250/32 and CR 250/19

8,700

9,600

10,200

Between CR 250/19 and US 19

9,500

9,600

8,300

Between US 19 and CR 56

19,700

22,800

18,800

Between CR 56 and CR 250/20

19,800

22,800

18,800

Between CR 250/20 and CR 64

19,800

26,000

19,600

Between I-79 and CR 73/73

21,000

24,200

19,600

Between CR 35 and CR 250/29

4,000

8,600

8,600

 

US 19

Northern County Line on US 19

2,200

2,600

2,400

Between CR 19/19 and CR 19/6

2,800

3,000

3,500

Between CR 19/6 and CR 17

5,400

5,600

5,800

Between CR 19/7 and CR 250/19

6,100

6,500

9,000

Between CR 250/19 and CR 19/8

12,000

13,000

12,000

Between CR 54 and CR 56

6,100

6,500

5,600

Southern County Line on US19

5,000

6,000

3,600

 

US 19 Spur

Between US 19 and US 250

14,600

17,100

11,700

 

WV 310

Between US 250 and Jefferson St. Bridge

10,000

12,500

8,500

Between I-79 and CR 66

5,000

6,500

6,500

Between CR 31/4 and CR 31/5

2,500

3,400

3,500

Southern County Line on WV 310

950

1,800

1,800

David Morgan Bridge

10,000

10,700

12,600

Table 5 - Fairmont/Marion County Multi-Modal Transportation Plan
Projected Future Traffic Volumes (2020)
Base + Committed Network vs. Recommended Plan Network

Facility

Approximate Location

1997 Volume

Base +
Committed

Rec.
Plan

Jefferson St Br

Jefferson Street Bridge

10,600

13,000

9,900

 

WV 218

Northern County Line on WV 218

1,600

1,900

1,800

Between CR 15/16 and CR 15/1

2,400

1,100

1,200

Between CR 15/1 and CR 20

2,800

3,900

3,400

Between CR 20 and US 250

3,200

3,600

3,900

Between CR 15/11 and CR 15/4

5,100

5,400

5,800

Between CR 15/5 and CR 52

5,400

6,800

6,100

Between CR 15/7 and US 19

6,100

6,400

7,000

 

CR 17

Between WV 218 and CR 18

1,600

700

700

Between CR 18 and WV 218

4,200

4,400

4,400

Between CR 17/2 and CR 17/4

2,200

2,400

2,400

Between CR 28 and CR 25

2,000

2,800

2,800

Between CR 17/11 and US 19

3,400

3,600

3,800

 

CR 1

Between CR 1/2 and CR 1/3

200

300

300

Between CR 1/3 and CR 3

550

600

600

Between CR 3 and CR 7

650

700

700

Between CR 1/10 and CR 9

1,600

1,700

1,700

Between CR 5 and US 250

2,500

2,800

2,800

 

CR 7

Western County Line on CR 7

400

300

300

Between CR 34 and CR 1

600

700

700

 

CR 64

Between WV 310 and CR 64/13

6,200

4,400

N/A

Between CR 64/13 and CR 64/5

4,900

3,400

N/A

Between CR 64/5 and CR 64/7

3,500

4,100

3,900

 

CR 11

Between US 250 and CR 11/1

1,500

1,900

1,900

Between CR 11/2 and CR 11/4

650

700

700

Southern County Line on CR 11

600

650

650

 

CR 58

Between CR 58/1 and CR 73/73

5,000

5,900

4,900

 

CR 58/1

Between CR 58 and CR 27

4,600

5000

2,800

 

CR 27

Between US 19 and CR 58/1

3,600

4,200

5,000

Table 5 - Fairmont/Marion County Multi-Modal Transportation Plan
Projected Future Traffic Volumes (2020)

Base + Committed Network vs. Recommended Plan Network

New Facility

Approximate Location

Rec. Plan

Rivesville Connector

Alignment A

7,000

Alignment B

7,500

Alignment C

10,000

 

1-79/Downtown Connector

All Alignments

15,000*

 

Eldora/Enterprise Connector

Between Eldora and CR 27

8,500

Between CR 27 and County Line

5,500

 

Coal Run Hollow Parkway

Jefferson Street Bridge to Locust Avenue Fairmont State College

5,900

 

US 250/US 19 Connector

US 250 to US 19

5,000

 

Third St. Br. (WV 310 Extension)

Third Street to Locust Avenue

8,500

* All alignments produce approximately the same future volumes.


FAIRMONT/MARION COUNTY MULTI-MODAL TRANSPORTATION PLAN
Final Report
Pflum, Klausmeier & Gehrum Consultants, Inc.