|
|
| Epoxy Coated
Reinforcement in West Virginia
|
Introduction
Until the early 1970s, West Virginia along with most other states
used black steel for reinforcement in nearly all reinforced concrete
structures. In slab structures such as bridge decks it had long been
noted that deterioration of the deck surface was directly related to
oxidation of the top mat of the steel reinforcement. As the
reinforcement oxidizes the tensile stresses produced are often higher
than the strength of the concrete. This eventually produces cracking and
spalling of the structure.
Although uncoated steel was being used, it was not considered
unprotected steel. Normal concrete s high-alkali environment passivates
the steel effectively preventing corrosion. Problems occur when either
of two occurrences happens - Carbonation of the concrete or the presence
of chloride ions. If either or both of these conditions are met the
steel will spontaneously begin to corrode or rust at localized areas.(1)
During this period in time a widely held belief was that if the steel
could be more permanently protected from exposure, oxidation could be
practically eliminated. This led to the development and use of epoxy
coatings. The use of these coatings has been the chief and in most cases
the only form of protection of steel reinforcement in West Virginia and
many other states. Since that time nearly all cast in place deck
structures in West Virginia have used epoxy coated steel reinforcement.
In 1992 reports began to surface that the epoxy coating practice was not
providing the protection for which it was intended. (2)
Previous studies involving the use of epoxy coated steel in Florida also
produced unfavorable conclusions and resulted in the cessation of
specifying the use of epoxy coated reinforcement by the Florida
Department of Transportation in 1988. (3)
Due to these and reviews of other reports, the Materials Control, Soil
and Testing Division of the West Virginia Department of Highways
instituted a study of the present condition of older bridge decks using
epoxy coated reinforcing steel.
The purpose as defined in the approved work plan for this investigation
was to evaluate the in-service performance of the referenced bridge
decks. The evaluation procedure included a thorough visual survey on
each deck with particular attention given to surface and subsurface deck
cracking. Evidence of rust staining would also be of particular
interest. In addition a complete delamination survey was performed using
the chain drag technique in accordance with ASTM D4580. The delamination
survey was used to identify only areas that were the result of
reinforcement corrosion. Areas indicating delamination, which could be
definitely associated with non-epoxy coated expansion devices or with
scaling, were not considered in this investigation. After these
processes were completed, areas exhibiting evidence of corrosion would
be further investigated by coring. It has long been a policy in West
Virginia to avoid coring bridge decks when there is no cause for
concern.
Investigation
All decks were surveyed between May and August of 1993. In order to
maintain uniformity the same personnel were used for all investigations.
This paper documents the investigation of fourteen individual bridge
decks that were identified as among the first using epoxy coated steel
reinforcement in West Virginia. These decks are identified in Table 1.
The bridges in this investigation served a wide range of traffic both in
numbers and type. The lowest average daily traffic (ADT) count was on
bridge numbers 2768 and 2776 with an ADT of forty. The highest count was
an ADT of 15,000 on bridge 2953. The type of traffic varied from bridge
2673 which had virtually no truck travel to bridge 2655 which had 62%
truck travel. The functional classification ranged from expressway sites
(2672 and 2668) down to rural sites (2776 and 2768).
| Project Number |
Bridge Number |
Year of Const. |
Area (sq.ft.) |
| APD 282(70) |
2930
|
1974
|
17,800
|
| HRR-19-16-3657 |
2953
|
1975
|
9,000
|
| ER-277(1) C-4 |
2776
|
1975
|
6,200
|
| 736(1) C-2 |
2771
|
1976
|
41,600
|
| BRF-0312(019) |
2665
|
1976
|
21,000
|
| I-79-1(38)10 |
2673
|
1975
|
17,000
|
| RF284(12) |
2655
|
1976
|
17,000
|
| BRF-0824(011) |
2847
|
1976
|
4,100
|
| BRS-0754(002) |
2975
|
1976
|
5,160
|
| ER-277(1)C-7 |
2768
|
1976
|
5,300
|
| I-79-1(38)10 North |
2672
|
1976
|
7,000
|
| I-79-1(38)10 South |
2672
|
1976
|
7,000
|
| I-79-1(39)7 North |
2668
|
1976
|
39,200
|
| I-79-1(39)7 South |
2668
|
1976
|
39,200
|
Caption: Table 1
Bridge
#2975 WV 37 East Lynn Bridge
Year constructed - 1976
Initial Investigation June 29, 1993
This is a two-lane deck with a pedestrian walkway separated by a
parapet. The deck is 172 feet long and 30 feet wide. The area of the
deck is 5160 square feet. No steel associated delamination. There is
what could be considered normal transverse cracking the full width of
the deck. These cracks are very light and are not associated with any
delamination. The only defects observable on the deck three small
circular spalled areas. The first two areas are approximately 8 to 10
inches in diameter and approximately 1/2 to 3/4 inches in depth. These
two areas are located at the center of the northbound lane 51 feet from
the southern end of the structure. The third area is located in the
southbound lane approximately 30 feet from the south end of the deck and
approximately 2 feet from the centerline. The depth of this spall is
approximately 1/2 inch. No delaminations were detected at these spalled
areas.
Bridge
#2655 US 52 Kermit
Year constructed - 1976
Initial Investigation July 21, 1993
The deck consists of two fifteen-foot lanes with a four-foot shoulder on
either side. The length of this deck is approximately 445 feet. The area
is 17000 square feet. The interesting aspect of the visual investigation
was the lack of defects. No patching, spalling or cracking was evident.
The bottom of the deck showed no signs of cracking. No delaminations
other than scaling associated with the expansion dams were detected.
Bridge
#2665 Rt. 2 Huntington Bridge
Year constructed - 1976
Initial Investigation July 28, 1993
This deck is a two-lane structure with an attached pedestrian walkway
opened to traffic in 1976. The deck is 584 feet in length with two
15-foot lanes and a 6-foot walkway separated from the traffic lanes by a
1-foot parapet. This comprises approximately 21,000 square feet. The
deck is slightly arched with the high point of the arch being
approximately 200 feet from the south end of the deck. Visual
investigation found no spalling or patches. Transverse cracking was
evident in much of the deck. No cracking was found in the deck north of
the north-end expansion device. In the immediate vicinity of the highest
portion of the slight arch, the transverse cracking was more frequent
occurring at approximately 2-foot intervals. In the remaining area of
the deck the cracking appeared approximately on 4-foot centers. Nearly
all the area of the wheelpaths had completely exposed aggregate. No
popouts were observed. The underside of the deck was not visible due to
corrugated metal (possibly forms) completely covering the bottom of the
deck. The delamination survey found no rebar-associated delaminations.
Delamination associated with the expansion dams occurred only on the
northern expansion dam in the southbound lane.
Bridge
#2768 Co. 37 Buffalo Creek
Year constructed - 1976
Initial Investigation June 14, 1993
The deck measured 116 feet in length with two 12-foot wide traffic lanes
and two eleven foot shoulders. The area of this deck is 5300 feet. No
spalling, patching, or cracking were observed on either the deck surface
or the underside. No delaminations were found in either of the two
traffic lanes or in much of the shoulders. Approximately 25% of the
shoulders could not be examined for delamination due to the large
buildup of rubble adjacent to the parapets.
Bridge
#2847 US 52 McDowell County
Year constructed - 1976
Initial Investigation August 3, 1993
This deck consisted of two 12-foot lanes and two 4-foot shoulder. The
length of the deck is approximately 130 feet and the area approximately
4100 square feet. Visually, there were no apparent deficiencies found.
The delamination survey found 1 area of approximately 1 square foot in
the Westbound lane. This delamination is located in the right wheelpath
approximately 138 feet from the Eastern end of the deck. The underside
of the deck exhibited no defects of any kind.
Bridge
#2673 I-79 Overhead Bridge
Year constructed - 1975
Initial Investigation June 9, 1993
This deck is not part of mainline I-79 but an overpass carrying a County
route over the interstate. Shoulder markings are not visible. The
dimensions of the deck are 42 feet by approximately 400 feet. The
two-lane deck encompasses approximately 17,000 square feet. An extremely
low number of cracks (approximately 12) were noted on the surface of the
deck. No delaminations were noted other than those associated with the
expansion dam devices located at either end of the deck and at the first
construction joint in from either end. The underside exhibited very
light cracking with some light efflorescence.
Bridge
#2672 I-79 Mainline Bridge
Year constructed - 1976
Initial Investigation June 8, 1993
Two decks are involved in this site. Both decks consist of two 12-foot
lanes, 1 twelve-foot shoulder and 1 four-foot shoulder. Each deck is
approximately 7000 square feet in area. No re-bar-associated
delaminations were noted in any portion of the two decks. A normal
amount of transverse cracking was observed with one exception. Each deck
was divided into 5 sections by construction joints. There was noticeably
more of the transverse cracking in the second and fourth section from
the southern end of the Southbound deck and the second section, again
from the southern end, of the Northbound deck. Again, this cracking did
not appear to be severe or out of the ordinary for decks of this age. It
is somewhat more unusual that the remaining section exhibited so little
cracking. The underside of the deck exhibited some light cracking and
associated efflorescence.
Bridge
#2776 Co. 37 Buffalo Creek
Year constructed - 1975
Initial Investigation June 14, 1993
The deck measured 136 feet in length with two 12-foot wide traffic lanes
and two eleven foot shoulders. The area of this deck is 6200 feet. No
spalling, patching, or cracking were observed on the deck surface. No
delaminations were found in either of the two traffic lanes or in much
of the shoulders. Approximately 25% of the shoulders could not be
examined for delamination due to the large buildup of rubble adjacent to
the parapets. The underside of the deck was not accessible.
Bridge
#2668 I-79 Big Sandy Bridge
Year constructed - 1976
Initial Investigation June 7,8, 1993
This is a 2-deck bridge with each deck approximately 980 feet long by 40
feet in width. The area of each deck is 39,200 square feet. In both
decks there was a noticeably higher number or transverse cracks in the
traffic lanes only. These cracks are four to six feet in length on
approximately four-foot centers. There are no delaminations associated
with this cracking pattern. The Southbound deck exhibited no
delamination. The Northbound deck contained one area of approximately
one square foot of delamination. This occurs 92 feet from the Southern
expansion dam almost directly on passing lane/left shoulder stripe.
There is also a popout approximately two inches deep associated with
this delamination. The underside of both decks was typical in that they
exhibited typical light cracking and some efflorescence.
Bridge
# 2771 WV 20 Hinton Bridge
Year constructed - 1976
Initial Investigation June 14, 1993
This two-lane deck with a separated pedestrian walkway is 1300 feet long
and approximately 32 feet wide. The area of the deck is 41600 square
feet. This deck visually was in very good condition. The typical light
transverse cracking was evident in only six of the fourteen panels
separated by construction joints in the deck. No delaminations were
encountered. One unusual feature was a large number of pop-outs, about
the size of an individual coarse aggregate particle, in the panel
beginning at approximately 327 feet from the Southern expansion dam. As
was stated, no delaminations occurred in this area and the depth of
these pop-outs was not sufficient to reach the top mat of the
re-inforcing steel. The underside of the deck was not accessible.
Bridge
# 2953 US 19 Adamson St. Bridge
Year constructed - 1975
Initial Investigation August 10, 1993
This is a two-lane deck with a separated pedestrian walkway. The
dimensions of the deck are 300 feet in length and 30 feet in width for a
total surface area of 9000 square feet. With the exception of one full
width transverse crack 175 feet from the Southern expansion dam, there
were no defects observable on the surface of the deck. This crack occurs
approximately mid-way between the two piers of the bridge. No
delaminations and no other cracks were found. There was a uniform
exposure of the aggregate on the entire surface of the deck, not just in
the wheelpaths. The underside of the deck was not accessible.
Bridge
# 2930 Industrial Bridge
Year constructed - 1974
Initial Investigation August 10, 1993
This deck consisted of two lanes and two separated pedestrian walkways.
The length of the deck is 557 feet and the width was measured to be 32
feet. The surface area is 17800 square feet. Delaminations were observed
in a number of areas on this deck. All linear measurements were taken
from the Southern end of the deck. At 37 feet, a delamination
approximately 2 feet wide extends for the width of both lanes. This
delamination is centered on a construction joint. At approximately 62
feet a one square foot delamination was present in the left wheelpath of
the Northbound lane. At 82 feet, a delaminated area was detected
approximately 1 foot wide and 6 feet in length. The area begins at the
pedestrian walkway parapet and extends into the Northbound lane
approximately two feet. At 250 feet, an area of approximately one square
foot in the right wheelpath of the Northbound lane. At 320 feet, an area
of approximately one square foot in the center of the Southbound lane.
The total area of all these delaminations is approximately forty square
feet. Some light, full-width and partial- width, transverse cracking was
observed. No delaminations were associated with any of the cracks.
Table 2 presents the results of
the delamination surveys performed on each deck.
| Project Number |
Bridge Number |
Year of Const. |
%
Delamination |
| APD
282(70) |
2930
|
1974
|
0.225
|
| HRR-19-16-3657 |
2953
|
1975
|
0.000
|
| ER-277(1)
C-4 |
2776
|
1975
|
0.000
|
| 736(1)
C-2 |
2771
|
1976
|
0.000
|
| BRF-0312(019) |
2665
|
1976
|
0.000
|
| I-79-1(38)10 |
2673
|
1975
|
0.000
|
| RF284(12) |
2655
|
1976
|
0.000
|
| BRF-0824(011) |
2847
|
1976
|
1.000
|
| BRS-0754(002) |
2975
|
1976
|
0.000
|
| ER-277(1)
C-7 |
2768
|
1976
|
0.000
|
| I-79-1(38)10
North |
2672
|
1976
|
0.000
|
| I-79-1(38)10
South |
2672
|
1976
|
0.000
|
| I-79-1(39)7
North |
2668
|
1976
|
0.000
|
| I-79-1(39)7
South |
2668
|
1976
|
0.002
|
Caption:
Table 2
Conclusions
Any conclusions made from this investigations must be based on the
evidence gathered. From this evidence several conclusions are apparent.
First, the bridges surveyed could be considered typical. The traffic
count data and wheelpath wear noted in the visual survey illustrates
that the bridges have and are carrying varying amounts of traffic.
Nearly all the decks exhibited transverse cracking on the deck surface.
This cracking was uniformly light and in no case was there any
delamination associated with the cracking. Prior experience would
indicate that most if not all the noted cracking could have been
shrinkage related. It is also important to note that none of the
cracking observed on the underside of the deck exhibited any signs of
rust staining. This would lead one to conclude that either no corrosion
was taking place in the deck or that no water was permeating out the
bottoms of the decks.
Another conclusion that can easily be drawn is that it is apparent that
for practical purposes there are virtually no delaminations present in
these decks. Ten of the fourteen decks physically had zero delamination.
Of the remaining four decks the percent delamination ranged from 0.002
percent to 1.0 percent. These percentages are from experience considered
insignificant. Again it should be repeated that these decks have had
nearly twenty years of service.
One factor that is not readily apparent from the data is to what extent
the decks have been subjected to chloride ions in the form of de-icing
salts. In West Virginia, the climate is such that there is normally no
extremely long periods of heat or cold. Located at the latitude that we
are and with the higher than average elevations, we do experience very
large numbers of freeze thaw cycles each year. In many ways this
produces greater problems for pavements and bridge decks that long
periods of one extreme. One of the problems associated with this type of
climate is the use of often-large amounts of de-icing salts deposited
each winter season.
The normal method of determining the chloride content present in
concrete is AASHTO test method T260. This involves drilling a test core
into the concrete to obtain specimens for laboratory analysis. As was
previously mentioned, it is not the normal policy of the West Virginia
Department of Transportation to core what are apparently sound concrete
structures. In this case, to positively determine the presence of
chlorides, four of these decks were tested in accordance with AASHTO
T260. The results of that testing is presented in Table 3.
| Project Number |
Bridge Number |
Chloride Content (lbs./cy) |
Year
of Construction |
| BRF-0312(019) |
2665 |
2.4 |
1976 |
| 736(1) C-2 |
2771 |
5.3 |
1976 |
| I-79-1(39)7 North |
2668 |
3.3 |
1976 |
| I-79-1(39)7 South |
2668 |
2.1 |
1976 |
Caption:
Table 3
Finally to illustrate the
difference between decks that have epoxy coated reinforcement and decks
that do not, data was analyzed on decks of approximately the same age,
usage and maintenance that did not contain epoxy coated reinforcement.
This data is presented in Table 4. As can be readily seen by comparing
the data taken from bridges with similar ages, chloride contents and
usage, there is a dramatic difference in the percentage of
delaminations. Of particular interest is in comparing bridge numbers
2668 and 2672 from the epoxy coated group with 2669 and 2670 from the
non-epoxy group. The reason for this particular interest is that all
eight of these decks are located on the same route within a four-mile
section. In fact the four non-epoxy decks are located between the four
epoxy decks. These decks must have been subjected to the same traffic,
weather, and maintenance conditions. The four deck employing epoxy
coated reinforcement exhibited a total of one square foot of
reinforcement associated delamination in a total area of 92,400 square
feet. The four decks not employ the coated reinforcement averaged 8.5
percent delamination. Visually, the major difference between the two
groups was the transverse cracking in the non-coated group was more
easily detected. No indications of rust staining were apparent on any of
the decks.
From the data collected in this investigation, it can be concluded that
the use of epoxy coated reinforcement in bridge deck in West Virginia
has resulted in a dramatic decrease in delaminated areas and therefore
an increase in the useful service life of these structures.
| Project Number |
Bridge Number |
% Delamination |
Chloride
Content |
| S350-37-30.06 |
2611
|
29.000
|
6.7
|
| S321-79-104.15
North |
2713
|
4.000
|
4.1
|
| S321-79-104.15
South |
2713
|
1.000
|
3.2
|
| S331-79-154.87
North |
2520
|
4.000
|
4.7
|
| S331-79-154.87
South |
2520
|
3.000
|
7.1
|
| S331-79-155.97
North |
2521
|
1.000
|
6.8
|
| S331-79-155.97
South |
2521
|
2.000
|
6.2
|
| S323-119-19.28
North |
2648
|
2.000
|
6.3
|
| S323-119-19.28
South |
2648
|
3.000
|
3.3
|
| S317-79-115.33
North |
2441
|
1.000
|
5.0
|
| S317-79-115.33
South |
2441
|
1.000
|
3.2
|
| S317-79-117.30
North |
2445
|
4.000
|
2.8
|
| S317-79-117.30
South |
2445
|
6.000
|
4.9
|
| S317-79-117.30
North |
2446
|
2.000
|
2.1
|
| S317-79-117.30
South |
2446
|
8.000
|
5.2
|
| S320-79-8.48
North |
2669
|
7.000
|
2.4
|
| S320-79-8.48
South |
2669
|
17.000
|
1.3
|
| S320-79-9.20
North |
2670
|
7.000
|
3.3
|
| S320-79-9.20
South |
2670
|
3.000
|
3.8
|
Caption:
Table 4
Footnotes
(1)- R.E. Weyers, B.D Prowell, M.M. Sprinkel and M. Vorster,
Concrete Bridge Protection, Repair, and Rehabilitation Relative to
Reinforcement Corrosion: A Method Application Manual, Strategic Highway
Research Program, SHRP-S-360, 1993
(2)- K. Clear, Effectiveness of Epoxy Coated Reinforcing
Steel, Canadian Strategic Highway Research Program, March 1992
(3) - L. L. Smith, R. J. Kessler and R. G. Powers, Corrosion
of Epoxy-Coated Rebar in a Marine Environment, Transportation Research
Circular No. 403, March 1993
|